Vashon Update November 19th
The Vashon Rough In of the Electrical Wiring and Plumbing Installation is Complete. We have Passed Our Electrical Inspection and the Exterior Siding is Close to Finishing.
Since our last Vashon build update we have passed our electrical inspection leaving only our low voltage work to be completed prior to installing insulation. Our Exterior Siding is 85% complete and should be wrapped up in the next few weeks. Additionally, we experienced a delay in getting PSE onsite to install our gas meter so we will notify our neighbors again when we receive an updated time frame.
- Vashon HVAC
- Vashon Low Volt Panels
- Warmboard Radiant Heating Progressing
- Vashon Rough In Complete
- Vashon Sliding Work Continues
- Vashon Sprinkler and Audio Installation