Vashon Update November 14th
Making Progress with Foundation Forming, PSE Gas Main and Neighbors Parking Pad.
The PSE gas main extension is complete. They brought new gas service from the west side of the Vashon Highway to the east side for this home. PSE provided free gravel for a neighbors parking pad and smoothed it out for them!
The foundation forming and reinforcement bar placement continued this week and into next week. We are planning on pouring concrete late next week or the week after depending on concrete availability. The concrete contractors are in high demand.