Vashon Update December 5th
Foundation Work Completed
The Vashon foundation work is complete. We began waterproofing the below grade foundation this week and plan on working Saturday to complete this phase. Onsite drainage work will start Monday 12/7.
Our foundation walls have been poured! All the forms have been stripped and removed from the site. The Vashon foundation damp proofing and insulation is ongoing and should be wrapped up by Monday, then we will begin foundation drainage work. The on site utility trenching and conduit installation will begin in the middle of the week.