Vashon Update April 22nd
All structural steel has been installed at Vashon and our wood framing continues and will be completed on 5/5/21.
We will then work on the “Drying-in” phase. Roof work will start mid-May and our sub-contractors will start working on all the “Rough-INs”. Starting with Fire suppression system, then plumbing, HVAC, and electrical. We expect this next phase to take about 8 weeks and there will be lots of activity.